Denver Gold GroupIndependent since 1989

Mining Forum Americas 2026 · Company presentation

Skeena Gold + Silver

Presented by Randy Reichert, President, Chief Executive Officer & Director

Moderator: Ralph Profiti, Principal, Equity Research Analyst, Stifel Nicolaus

Monday, 28 September 2026, 15:30 MDT · Bartolin: Stage 2

  • TickerTSX:SKE
  • Market cap$3.9B
  • 1-year return67.50%
  • StageDeveloper
  • Primary metalGold
  • Primary countryCanada
  • Reserves4.6 Moz
  • M&I resources0.9 Moz

In brief

Randy Reichert of Skeena Resources provides an executive-level status update on the Eskay Creek gold-silver project in British Columbia. The presentation outlines the company's progress through a transformative year of permitting, financing, and construction, highlighting the path to Q2 production. Detailed analysis covers the project's tier-one economics, de-risking milestones, technical design updates, and the transition toward full operational readiness within the prolific Golden Triangle.

Key moments

  1. Eskay Creek Asset Potential

    “It's gonna be one of the highest grade open pit mines in the world.”

    Skeena's Eskay Creek is a tier-one gold and silver asset positioned to be one of the highest grade open pit mines globally.

  2. Refinancing and Capital Structure Strategy

    “It was one of the first times that a pre-production company has been able to do this.”

    Skeena achieved a major financing milestone by issuing senior secured notes, lowering their cost of capital significantly.

  3. Project Construction and Timeline

    “Our first ore is expected in Q2 of this coming year.”

    Construction of the Eskay Creek project remains on track, with the first ore extraction targeted for the second quarter.

  4. Metallurgy and Ore Processing

    “Eskay Creek has almost no free gold. We don't even put in a gravity circuit into it.”

    Eskay Creek ore requires ultra-fine grinding because it contains almost no free gold, contrasting with historical high-grade deposits.

Portrait of Randy Reichert

Presenter

Randy Reichert

President, Chief Executive Officer & Director, Skeena Gold + Silver

Mr. Reichert has 40 years of experience in the mining industry and prior to joining Skeena, was the Vice President of Operations at B2Gold Corp. where he oversaw their three international gold operations. Before his most recent role at B2Gold Corp, Mr. Reichert was the General Manager at their Fekola Mine in Mali where he was part of the development team and led the transition from development into operations. He started his career with Cominco in Canada working at various operations including the Snip Mine. He then embarked on international work with Bema Gold, Oriel Resources, and other junior companies in executive roles where he was responsible for various development projects and mining operations. Randy has led construction or development projects in Russia, Brazil, Nevada, and Kazakhstan and was General Manager during the development of the Kupol Mine in Russia with Bema Gold and subsequently Kinross. He also has experience as a consultant assisting with due diligence for mine financings for Canadian financial groups. Mr. Reichert has a BA.Sc. in Mining and Mineral Processing, a MSc. Eng. in Rock Mechanics, a Graduate Diploma in Business Administration and is a Professional Engineer.

About Skeena Gold + Silver

Skeena is a leading precious metals development company focused on advancing the Eskay Creek Gold-Silver Project in British Columbia’s Golden Triangle. With the Project fully permitted and under construction, the Company is progressing Eskay Creek towards initial production and cash flow in the second quarter of 2027. Once in operation, Eskay Creek is expected to be one of the world’s highest-grade and lowest-cost open-pit precious metals mines, with significant silver by-product production that exceeds the output of many primary silver mines. Skeena is committed to responsible and sustainable mining in partnership with Indigenous communities, while maximizing the value of its mineral resources to generate long-term shareholder returns.

Transcript2800 words, automatically generated

This is an automatically generated transcript. Denver Gold Group cannot accept responsibility for mistakes, errors, omissions, or any action taken in reliance thereon. Use of this transcript is governed by Denver Gold Group’s Terms of Use.

Thanks, everybody, for joining us today. Gonna talk today primarily about Skeena’s flagship operation, Eskay Creek, and the development we’re doing on that today. Gonna start here. I will be making a number of forward-looking statements today, and I guide you to this and to the statement here.

Eskay Creek is a rare tier one gold, silver opportunity in Canada. It’s gonna have large-scale gold and silver production, about 450,000 equivalent ounces over the first five years. It’s gonna be one of the highest grade open pit mines in the world. All of that translates into low operating costs in a great area of the world. Mining’s very common there, very well known. Construction is now majorly underway. We’re approaching over 70%, approaching the 75% mark, and we do have growth opportunities at Eskay ahead of us.

2026 is really a year of execution for us. It really started in January where we first signed an IBA agreement with the Tahltan First Nation in BC, along with the Section 7 agreement there. We got our environmental assessment certificate and our major mines permits, but that all before the end of the first week of February. We went on then to do a comprehensive refinancing package. I will get into that a little bit in the next few minutes. But as well, what we’ve really been doing is a lot of de-risking.

We did come up with a CapEx estimate for Eskay Creek redevelopment in the end of March. It’s about 20% higher than what we had put out in the DFS, but still very much in line to about $659 million US to do that. Some of the cost escalation there was partly inflation. Some of it and quite a bit of it was water management with some of the regulations in BC tightening up over the time that we did the engineering and the permitting. And then finally, a few design changes that were cognizant just to make the project a lot better.

Eskay Creek is situated in the Golden Triangle in northwest BC. It’s in an area of the world that’s very well known for mineralization. Couple operating mines nearby, Red Chris and Brucejack, both Newmont assets. There’s other really big development projects there as well. It’s got excellent infrastructure, paved highway to within 55 kilometers of Eskay Creek, and excellent gravel road all year round access into the site. And one of the most important things, about 300 megawatts of power generation about 17 kilometers away from Eskay Creek that ties into the BC Hydro grid. So great, great infrastructure.

If we take the now almost three-year-old DFS, apply updated current metal prices, we end up with an NPV of around $5.5 billion US and a very, very quick payback on this asset. Through years one to ten, you can see, based on that, very, very high cash flow generation from this asset. We will be coming out with a new update on this towards the end of January, update some of this, the free cash flow metrics, operating costs, et cetera.

When we put out the DFS, we front-end loaded the production profile. So excellent profile over the first five, six years, averaging about 450,000 gold equivalent ounces over that time, and then the grades started to drop off. But we knew that we had opportunities to bring that back up. So five and a half grams a ton average over the first five years is one of the highest grade open pit gold mines in the world. Excellent all-in sustaining costs. We will be updating those shortly.

What we’ll be doing, though, by the end of January is updating the technical report, bringing in really a couple main things: steepening the pit slopes to deepen the pit, and as well bringing in our SNIP asset as well, keeping it as a small underground mine, but bringing it into operation. So we fully expect Eskay Creek to be able to show that it’ll run at a run rate of about 400,000 ounces over ten years’ time. So a great asset and a great jurisdiction.

This is the refinancing that we did, I guess it was really the first week of April. This kind of points to Skeena and how we think about things, and we’re not really looking for norms. This is about out-of-the-box thinking. We refinanced a package that we had done with Orion. It was a really good package, $350 million US senior secured loan and another $100 million cost overrun facility. As well, we used, to pay back or buy back two-thirds of the stream, and we did this by issuing a $750 million US senior secured note. It was one of the first times that a pre-production company has been able to do this. It brought our cost of capital down from about 12% to about 8.5%. It was very well received in the market, and now we’re starting to see others do the same. But it was excellent thinking by Waltz to get that done.

If we look at North American jurisdictions for gold production, we’ll see that in the first five years, Eskay Creek will rank one of the biggest producers. Over the life, it’s still very high. But again, we believe that that average, we’re going to go up as we continue to improve Eskay Creek and look at the growth opportunities there. If you look at the bottom line there, you’ll see who most of these assets are belong to. So most of the top ones always in the hands of seniors and majors. So we’ve got a real prize asset on our hands here.

I talked about the gold grade already. This just shows where we’re at, about 5.5 million, 5.5 grams per ton over the first five years. As well, we’ve got 4.6 million gold equivalent ounces in reserve right now, but 80% of that is in the proven category. So we’ve got a very, very high confidence on that. And then we do expect that to grow and grow fairly significantly over the next, say, call it four months.

So I mentioned we’re in the middle of construction right now. It’s progressing very well. I’m going to draw a line here. So we’re kind of right around here today. What do we have left is really now where we’re at. So permanent power is almost up to site. So we’ll tie into the lines. We’ll energize in late November. Tailings dam, the small starter dams that we have will be done that in probably the next month and a half to two months. Mining’s been ongoing for really, we started it in 2024, got bigger and better last year in ’25. And now we’re really putting in the pit mining practices. And I’ll show you some pictures on that. In the next week, we’ll start now taking ore out of the pit and stockpiling it.

In terms of the production, the process plant, it’s progressing nicely. Mechanical installation is almost complete. It’s really about piping and electrical and instrumentation right now. The only mechanical we have left is kind of the jaw crusher and the filter press to go. And that’s really left. Camp is almost complete. So this is the big thing here, though. Our first ore is expected in Q2 of this coming year. We’re tracking very nicely towards that and very confident that we’re going to achieve that.

This is what we’ve done basically on the project to date. So bulk earthworks mining, we started that. We’re doing all our own mining and earthworks on the project. Advanced that nicely. I’ll show you some pictures. Wastewater management, again, we’re building that out. We’ve put in water treatment plant. Phase two of that is going to come online in the next couple of months. Process plant is being done by Ausenco under an EPCM contract. It’s going very well. High voltage is almost in place. And then, of course, the camp.

This just quickly shows the site layout and what it looks like. The pit over in here. All the ore mining is starting up towards the top of the ore body, and it comes down a ridge. When we look at the processing plant, it’s pretty straightforward. Jaw crusher followed by three stages of grinding. We then do a rougher float followed by a regrind. And following that regrind, a cleaner, and we produce a concentrate. And right now, we’ll only produce a concentrate from Eskay Creek and sell it to smelters and mostly begin with probably go to China.

Here’s some pictures just to show you some of the progress for what we’re making. This is the open pit that we’ve really started. In the foreground of the pit, this is what we’ve been mining, mostly to get clean NAG waste materials for building out the infrastructure like roads, coarse ore stockpile, and the tailings dam, the starter dam. Now our focus is really moving on the ore mining. And the ore mining is up in this area here. So we’re mining predominantly rhyolite over the next year, starting to take that out in the next week, as I mentioned, and we’ll progress that. Want to have about 250,000 tons of ore on the stockpile prior to startup.

Crusher conveyor installation on the left, that MSC wall now is just about complete. You can see the steel work and some of the mechanical installation of the jaw crusher there. On the right is the conveyor that goes from the crusher over up to the coarse ore stockpile. That conveyor is all in place now. Here’s the before and after. On the left is the coarse ore stockpile reclaim area. And on the right now we’ve got it backfilled and we’re currently doing the ring concrete foundation for the dome installation, which is expected to start the frame installation this week.

Mechanical installation of the plant going very, very well, probably over 90% complete now. We’ve got SAG mill in, ball mill in. We’ve got our two, in blue there, is our Isa mills, one’s a tertiary mill, and then our concentrate regrind mill. On the right, our flotation, that’s our rougher flotation tank cells. And then this photo is kind of the one that I like. So it kind of shows the mill looking from the dryer and filter press over towards the north. And you can see there’s not much room to put anything else in, so the mechanical installation here is progressing very, very nicely.

Water treatment plant phase one is done, and we’re just about complete with phase two. We’ve also got now the Volcano Creek substation is complete and ready to tie in and energize the system. On that, we’ve got poles to within two kilometers of the site, and our lines are strung up to about five kilometers from the site. So that’ll be done over the next month, then towards the end of November, we’ll energize in our final tie-ins.

New employee camp that we’re putting in is gonna be state-of-the-art, best in the area by far. Three-story facility. We’ve situated about ten kilometers away from the mine. It’s in an area that gets about a third of the snow. It’ll be a great employee experience. In terms of what it looks like inside, very solid, brand-new kitchen, dining facility. On the right, beds that are slightly bigger than the norm for most camps in Canada. And as well, every single room has its own washroom, which is huge when you go to recruit and for retention of personnel. So we’ve put some money into this, but knowing there’s a good reason for it.

We’re now really moving into the operational readiness phase. So part of that is the mining. The mining’s been going on for a while. What we’re really doing in the mining now is zeroing in on our selective ore mining techniques. So we’ve been mining fairly bulk waste before, but now some of the things we’re putting into place, we’ll use selective flitch mining with backhoe excavators. And then we’ll use some technology to really help guide the excavator and the dig lines.

People is a big focus right now. A lot of recruiting. We do have our GM in place. We’ve got mill manager in place, mine manager in place, maintenance people in place, chief mets, and the like. So we’re finishing off our commissioning plan right now, and then we’ll bring in some operators and help. We’ll split the commissioning between us and Ausenco to do that. The other thing we’re doing is quite a bit of met testing ahead. So we’re gonna drill some samples very much indicative of the first twelve months of ore that’ll go through the plant to do that, just to help guide that ramp-up phase of the mill and have the operators know exactly what to expect.

This is the Lassonde curve and of course fairly well-known. We followed that pretty well to a T so far. We’re sitting today at about a $4 billion US market cap. We do see a lot of growth opportunity from here. We believe there’s gonna be some re-rates from here, I’ll get into that in the next slide, but there’s some good comps to look at here in terms of comparing our production profile, our free cash flow profile with what some of these other companies are doing and what their market caps are. And I think it bodes well, and it really shows where we expect to be in the next six months to two years.

If you look at some of the other developers who are now in production, and they’ve looked at their re-rate over the time of development and getting into production, it bodes well for Skeena and what we’re expecting over the next kind of period of time. Again, market caps, when you look at it and where we’re at, and we’ve got this pathway of 500,000 ounces of production in 2028. Again, we see the first re-rating going when we start commissioning and we start putting ore through the mill. We see then another re-rating when we get proven that we can operate this mine and generate the free cash flow that we say it’s going to.

Really, really good shareholder support, really good coverage from the banks. Here’s the list of our shareholders. There’s been a couple of them in the last couple years that have come in totally on the open market, and good supporters. I’ll leave it there if there are any questions.

Thanks very much, Randy. We do have time for one question. John?

Hey, Randy. John Tomasso.

Hey, John.

You had early experience at Kupol, which was a very high-grade deposit with a lot of free gold.

Yeah.

How would you compare Eskay? Free gold to Kupol. And in terms of the geostatistics and the technical studies for Skeena, do you think the top cuts were liberal, loosey-goosey, too much area of influence? Are you building a beautiful grinding mill with the ore grade kind of fuzzy?

Yeah, so interesting. First of all, Kupol, yeah, lots of free gold. Eskay Creek is the exact opposite. Eskay Creek has almost no free gold. We don’t even put in a gravity circuit into it. It is all very, very super fine. And in fact, to get the full liberation, we have to grind down to ten microns to get it. So it is a completely different beast.

Now, when we go back and look at the production history of Eskay Creek, their reserve estimate grade over the life of the mine was underestimated always. So they would overproduce pretty well all the time. I liken this a lot actually to Fekola and Mali, because at Fekola and Mali, we see extremely high grades as well. And overall, what we saw in Mali was that the higher grades, actually we’d always get a bump up on the reconciliation, not a drop down. In the lower grade, we’d actually see it the opposite way. This is what historically has been at Eskay Creek as well. So no, I don’t think there is any liberalism at all in any of the top cuts. This is a deposit that’s been known for many, many years. And like I mentioned, production profile over the life, they always had underestimated the reserve grade and ounces on it and always overproduced on that.

That’s all the time we have. Please join me in thanking Randy for his presentation. [audience applauding]

Recorded at Mining Forum Americas 2026, The Broadmoor, Colorado Springs. Prepared for information only; it is not investment advice or a recommendation. Statements are those of the presenting company as at the date of the presentation. Market figures in US dollars, not as at the date of the forum.